This section enlists all the undertakings/Self attestations and Indemnity Bonds that are to be submitted according to the details given in the following forms:
2.12.6 Undertaking/ Self-Attested certificate on plain paper to be given by an Architect/ Engineer that he has been appointed by the Owner and countersigned by the owner. Please refer to Form A-2.
2.12.7 Undertaking/ Self-Attested certificate on plain paper to be given by the
Structural Engineer that he has been appointed by the Owner and countersigned
by the owner. Please refer to Form A-2.
2.12.8 Undertaking/ Self-Attested certificate on plain paper to be given by the
Supervisor that he has been appointed by the Owner and countersigned by
owner Please refer to Form A-2. 2.12.9 Indemnity Bond by the Owner(s), in case basement is to be constructed. Please refer to Form A-7.
2.12.10 In case of a Low Density Residential Area, NOC from the Competent authority from land acquisition point of view to these bye-law clause no 6.4
(Regularization of Farm Houses).
2.12.11 Approval of the Chief Inspector of Factories in case of industrial buildings; and also from the Pollution Control Board, wherever required.
2.12.12 Approval from Chief Controller of Explosives, Nagpur and Delhi Fire Service, in case of hazardous buildings wherever permitted.
2.12.13 Land use / use / premise clarification from the Delhi Development Authority regarding land use as per Master/Zonal Plan, if required.
2.12.14 In case of high rise buildings a technical report from Geo-Technical Engineer shall be incorporated in the structural design submitted.
2.12.15 Any other document/proforma required by the Authority / concerned local body or department/ organization, as deem fit.