Chapter 2- Procedure and Documentation for Sanction/ Completion of Building Plans, Section 2.26 Communication for Occupancy/ Completion Certificate

The Authority/ concerned local body on receipt of the notice of completion along with mandatory documents, shall inspect the building/work after communicating the schedule of inspection to the Owner.
318 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
2.26.2After inspection, Objections, if any, and compounding fee, to be calculated for compoundable items given in Annexure IV, shall be intimated to the Owner.
2.26.3On compliance of all requirements, the Occupancy/ Completion Certificate shall be issued within a period of 30 days.
a. Communication regarding issuing of completion is communication by
Authority/ concerned local body. Please refer Form D-2
b. Communication in case of rejection, giving full reasons and objections
raised are Communication by Authority/ concerned local body.
Please refer Form D-3